Scope of Works
Replacement of the existing pipe-and-slit-drained Fibresand pitch with a new stitched hybrid pitch. The pitch works were completed to first use in nine weeks.
- Excavation and removal of the existing pitch profile
- Excavation and removal of 30,000 tonnes of subsoil to reduce pitch crossfall from 1 in 50 to 1 in 100
- Installation of new drainage system
- Installation of gravel carpet
- Installation of base-sand rootzone
- Installation of upper rootzone
- Installation of new undersoil heating system
- Installation of new irrigation system
- Installation of stitched hybrid reinforcement system
- Seeding and grow-in
Scope of Services
- Pitch assessment and feasibility report
- CDM Health & Safety Principal Designer
- Design and tendering
- Contract management
- Key-stage inspections
- Sign-off and handover